Facilities Steering Committee, March 26, 2014

GUNN HIGH SCHOOL

FACILITIES STEERING COMMITTEE

March 26, 2014

In attendance: Lori Larson and Tom Hodges (construction coordinators), Kim Cowell (asst. principal), Tarn Wilson (teacher), Lisa Hall (SAC advisor and teacher), Anne Marie MacRae (PTSA parent), Lynne Navarro (teacher), Laurie Pennington (teacher), Shivani Pulimamidi (Special Ed. supervisor). Notes taken by Martha Elderon.

I. CENTRAL BUILDING PROJECT, SCHEMATIC DESIGN

  • Two music classrooms (for choir and band/orchestra) will be attached to the Quad-side of Spangenberg lobby, and a separate ticket office will be built closer to the parking lot.
  • In the two-story building across the Quad from Spangenberg, the first floor will contain the SAC, two flexible classrooms, two offices, a copy center, and storage space.
  • The second floor will contain the College & Career Center, a wellness center, three Social Studies classrooms, offices, presentation space and a conference room.
  • Lori Larson and Tom Hodges met with Gunn representatives from the Music Department, Oracle newspaper, and Yearbook to discuss space allocation.

 

II. VILLAGE PORTABLES & CLASSROOM REARRANGEMENT

  • Ideally all Social Studies classes will be grouped near each other (in C and E buildings), eliminating the need for Village classrooms.
  • Focus on Success and Opportunities classes will relocate to K1 and K2 respectively.
  • The Social Studies/Science offices will remain in the K building.
  • One F-building classroom will become available for Social Studies when the new SpEd classrooms are completed in the K building.

 

III. E & K BUILDINGS

  • The E building (formerly L31) will contain two regular-sized (960-square-feet) classrooms and the new Gunn Tech office.
  • Technology offices will move from the library to the E building to be more centralized.
  • Shades for privacy are needed in all K-building Special Ed. classrooms.

 

IV. MIRANDA AVE. DROP-OFF

  • The backroad parallel to Miranda Ave. is currently under construction and should be ready by June.
  •  Paving will be installed over Spring Break.
  • Staff parking spaces may be available in May, though the turnaround area will take longer.
  • City permits for traffic signals are still in process.
  • The Gunn organic garden will return to the back-road dropoff area when construction is completed.

 

V. REIMBURSEMENT FOR MOVING TIME & FUTURE DATES

  • Teachers will most likely be paid for up to 14 hours of moving time.
  • E and K buildings should be remodeled by August 8, 2014.
  • The next Facilities Committee Meeting is May 14, 1pm in the Staff Lounge.

 

 